Gia Binh and its community: early land handover bonuses paid and Ngo Thon heritage sites rebuilt
Credit: Masterise Aviation Infrastructure
472 households that handed over land early have received a second bonus payment, while the communal house, pagoda and parish church of Ngo Thon are being rebuilt in a new resettlement area.
As construction of Gia Binh International Airport (GBIA – ICAO VVGB, IATA GBN) moves ahead, the project is also investing in the communities around the site, from support for households that handed over land to the careful rebuilding of local heritage.
Bonuses for early land handover
- On 31 October 2026, the Gia Thuan land fund development centre, together with Gia Binh ward and the investor, paid a second round of bonuses to 472 households that handed over land early: 109 in Luong Phap, 136 in Ngo Thon and 227 in Thu Phap.
- Each household received VND 50 million, a total of VND 23.6 billion.
- Earlier, Masterise Aviation Infrastructure (MAI) paid VND 100 million to each household that handed over land within the APEC project area.
A new home in Dong Cuu 1
The Dong Cuu 1 resettlement area covers 30.03 hectares, of which 17.36 hectares are for housing, with 19 blocks and almost 600 residential plots. Essential infrastructure is largely complete, and 200 households registered for plots within the first 19 days.
Rebuilding Ngo Thon’s heritage
- MAI is speeding up the rebuilding of the Ngo Thon communal house, pagoda and parish church in the resettlement area, covering about 10,000 m². Work began in July–August 2026 and is expected to finish in June 2027.
- The original timber components of the communal house and pagoda have been carefully dismantled, treated and stored, ready to be reassembled once the foundations are complete.
- A new Gothic-style parish church of about 500 m², with a 36.1-metre bell tower, is being built.
Respect for local communities and their cultural heritage is part of how Gia Binh is being built, alongside the airport’s preparations for APEC 2027.
As things stand, the tentative key dates are: the airport officially opens on 31 May 2027, starting with the VIP terminal; the direct expressway to Hanoi opens at the end of October 2027, bringing the journey to about 25 minutes; and the commercial passenger terminal follows as a separate phase.
Source: CafeF (from Việt Nam Hàng ngày), 3 November 2026.