Vietnam studies moving international operations from Noi Bai to Gia Binh
Credit: Masterise Aviation Infrastructure
The Government has asked agencies to study an operating plan for Gia Binh International Airport, including an option to move all international operations from Noi Bai. Technical test flights are expected by the end of 2026.
Vietnam’s Government has asked the relevant agencies to study an operating plan for Gia Binh International Airport (GBIA – ICAO VVGB, IATA GBN) that includes an option to move all international operations from Hanoi’s Noi Bai International Airport to Gia Binh, Deputy Minister of Construction Bui Xuan Dung said at a meeting in Hanoi on 9 November 2026 chaired by Hanoi People’s Committee Chairman Vu Dai Thang.
What is being studied
- Under the proposal, Noi Bai would continue to handle domestic flights and some international services during 2029–2030. A further airport south of Hanoi is planned for a later stage.
- Gia Binh is oriented as an international airport that will also handle domestic flights. The split of passengers and flights between the two airports has not yet been decided.
- Noi Bai is planned for 50 million passengers a year by 2030 and 100 million by 2050. Gia Binh is planned for 30 million passengers and 1.6 million tonnes of cargo a year by 2030, rising to 50 million passengers and 2.5 million tonnes by 2050.
Faster rail links to both airports
Authorities are reviewing metro and rail routes to cut travel time between central Hanoi and either airport to around 30–45 minutes, possibly with limited-stop airport express trains. Options include the shortest rail link from Gia Binh to central Hanoi via Gia Lam station, a major interchange at Gia Lam for national, high-speed and urban rail, and a direct rail link between Gia Binh and Noi Bai so that international passengers can connect easily with domestic flights. The Vietnam Railway Authority is coordinating the review.
Update, 16 November 2026
Do Hong Cam, Deputy Director of the Civil Aviation Authority of Vietnam (CAAV), said the operating plan for Gia Binh is being drafted and will go to ministries and agencies for one to two months of consultation before it is finalised. Technical test flights at Gia Binh are expected by the end of 2026. The start of commercial operations will depend on decisions on routes, airlines and any transfer of flights from other airports.