Gia Binh (GBN) construction update: ATC tower, runway and VIP terminal take shape ahead of APEC 2027
Credit: Nam Tran / Tuoi Tre
The ATC tower structure is essentially complete, runway pavement works are under way and the VIP terminal roof is going up at Gia Binh International Airport, as calibration flights begin.
Fifteen months after construction began in August 2025, the key works for Gia Binh International Airport (GBIA – ICAO VVGB, IATA GBN) in Bac Ninh are taking shape on site, with the airport preparing to serve the APEC Leaders’ Week in 2027. A photo report by Tuoi Tre in late November shows the progress across the airfield.
Air traffic control tower
The main structure of the tower is essentially complete, and work is moving on to the control cab. The ATC office buildings alongside are at the rough-finishing stage, with electrical, water and technical systems being installed.
Navigation aids
The structure of the DVOR/DME station is essentially finished, and engineers are installing the navigation equipment. The airport’s navigation systems include DVOR/DME and ILS, with the airport designed for CAT III approaches. The first flight inspection of the DVOR/DME system was carried out by ATTECH on 24–25 November 2026, with further calibration and test flights to follow.
Runway
- Soft-soil treatment, sand fill and the crushed-stone base are complete.
- Pavement layers, including geotextile and geogrid, are now being laid, to be followed by two layers of cement concrete; the top concrete layer is being prepared.
- Drainage and airfield ground lighting are being accelerated, with work highly mechanised and supervised by Vietnamese and international consultants.
The runway is designed for wide-body aircraft including the Boeing 777 and Airbus A380, alongside a parallel taxiway and apron.
VIP terminal
The steel structure and mechanical, electrical and plumbing works of the VIP terminal are being completed, and its roof is going up. The sweeping curved roof draws on the traditional temple and pagoda architecture of the Kinh Bac region. The building will welcome heads of state, senior leaders and international delegations.
Built to international standards
Gia Binh is designed to ICAO Code 4F and a five-star service standard, with capacity of 30 million passengers and 1.6 million tonnes of cargo a year by 2030. Vietnam’s National Assembly approved the project in December 2025, with total investment of more than VND 196,000 billion.
As things stand, the tentative key dates are: the airport officially opens on 31 May 2027, starting with the VIP terminal; the direct expressway to Hanoi opens at the end of October 2027, bringing the journey to about 30 minutes; and the commercial passenger terminal follows as a separate phase.
Airlines and partners interested in Gia Binh International Airport are invited to contact [email protected].
Source: Tuoi Tre, 25 November 2026.